Infrastruktur Mubazir, Revisi Permen ESDM 19/2009
Regulation on Exploration Geothermal Should Be Revised
Reporter : Gatot Priyantono
Editor : Cahyani Harzi
Translator : Dhelia Gani
Jakarta (B2B) - Badan Pengatur Hilir Minyak dan Gas Bumi (BPH Migas) meminta pemerintah merevisi Permen ESDM 19/2009 tentang Kegiatan Usaha Gas Bumi melalui Pipa.
Direktur Gas Bumi BPH Migas Hendra Fadly mengatakan akibat implementasi permen tersebut, kini banyak trader gas yang juga membangun pipa di wilayah yang sebenarnya sudah ada infrastruktur pipa.
“Menurut kami Permen 19/2009 harus ditinjau lagi, karena kondisi di lapangan itu dinamis. Itu perlu direvisi untuk menghindari pipa-pipa yang dibangun bertumpuk-tumpuk,” kata Hendra.
Hendra mengatakan selama ini PGN tidak ingin pipanya dilewati oleh pihak lain, sehingga diterbitkanlah aturan itu yang memperbolehkan trader gas membangun pipanya sendiri. Tapi akibatnya, di wilayah yang sama dibangun pipa bertumpuk-tumpuk, seperti yang terjadi di Jawa Timur, hal ini berujung pada harga jual gas yang lebih tinggi di tingkat konsumen.
“Tapi ternyata semua trader ingin membangun pipa sendiri, akhirnya harga ke konsumen jadi lebih mahal. Padahal konsumennya juga berdekatan. Apa salahnya memanfaatkan pipa yang sudah ada?,” ujarnya.
Dalam Permen 19/2009 pasal 10 disebutkan dalam hal dari aspek teknis dan ekonomis pipa transmisi dan/atau pipa distribusi tidak dapat dimanfaatkan bersama atau belum tersedia, maka badan usaha dapat membangun pipa dedicated hilir.
Jakarta (B2B) - Downstream Oil and Gas Regulatory Agency (BPH Migas) asked the Government to revise regulation no 19/2009 exploration geothermal using pipeline.
The BPH Migas Geothermal Director Hendra Fadly said that regulation is actually triggering a lot of gas traders to build pipe line in the area where pipe line infrastructure has already existed.
“According to us, considering the dynamic field condition, the regulation no.19/2009 should be re-examined in order to avoid overlapping in pipe line installation,” said Hendra.
Hendra made clear that, PGN did not want their pipeline is overlaid by other pipe installation so that BPH Migas issued the regulation which allowed gas traders to develop their pipe installation. However, it actually triggered highly gas selling price in area where overlaying-pipe installations are developed such as in East Java.
“Since the traders intend to develop their own pipe installation, which by the end of the day would impact higher gas selling price for local-consumer. Therefore, why we don’t utilize the existing pipe installation?” said Hendra.
Meanwhile, regarding the regulation point number 10, both pipeline transmission and distribution couldn’t be collectively utilized yet so that the traders could build downstream dedicated pipe.